Internal
Infrastructure
•
Key internal infrastructure needing
development is: Road, Electrification,
Water supply, Sewerage, and Arboriculture.
The total cost of this development
is estimated at Rs 1151 crores.
• While
the SEZ area is broadly undulated,
leveling and reclamation (in an
area of around 300 Ha) are essential
to avoid high tide water flows.
The cost of these is stimated at
Rs 120 crores. Holding ponds will
also need to be created (covering
an area of 195 Ha) and are estimated
to cost Rs 53 crores.
• Construction
of roads in the SEZ area is estimated
to cost Rs 220 crores.
The SEZ area receives heavy rain
falls and would require construction
of storm water drains and water
channels. The cost of these is estimated
at Rs 174 crores.
• Construction
of elevated storage reservoirs and
ground storage reservoirs is estimated
to cost Rs 96 crores. While Rs 26
crores would be required for construction
of nodal feeder pipeline and related
works. Sewerage and water supply
facilities have been estimated to
cost Rs 75 crores and Rs 49 crores
respectively.
• Arboriculture,
landscaping and development of a
green belt are estimated to cost
Rs 5 crores while development of
about 40 gardens is estimated to
cost Rs 12 crores.
• The
SEZ area will be bonded by a 18
feet high boundary wall which is
expected to cost Rs 42 crores.
• Non
saleable social infrastructure facilities
are estimated at: Truck terminal:
Rs 4 croes, Helipad: Rs 4 crores,
Fire stations: Rs 4 crores, Police
stations: Rs 2 crores, Bus stations
and taxi stands: Rs 4 crores, Community
centers, common toilets and other
facilities: Rs 3 crores.
|
|
| |
|